Latest construction projects from Neary are shown below. Click on a project name for full details, or use the page functions to view any previous projects.
Western Power Distribution | Construction
Due to a third party 132kV cable strike on the main 125mph rail line at Hams Hall near Cannock there was a necessity to install a new duct run underneath both the inward and outward tracks. Jointbays were constructed either side of the main line in order to re-joint the damaged cable.
Prysmian (Ultimate Client : Central Networks (now WPD) | Construction
This scheme, located near the centre of Birmingham, involved the re-routing of an existing circuit into (and back out of) a refurbished substation.This was achieved by installation of 2 No.
Siemens (Ultimate Client : Central Networks) | Construction
Due to faults occurring on two Grid Transformers it was necessary to remove the roof and knockout front wall panels from two of the four transformer complexes on site.The works involved the careful dismantling of the noise enclosure roof to the transformer whilst the remainder of the site remained live.
Siemens (Ultimate Client: Scottish Power) | Construction
The works involved the removal of an existing 132kV Transformer (by others) and then our subsequent excavations and core drilling in to deep bedrock.The rock slopes were then retained with a specialist Rock Netting system to ensure the integrity of the equipment at the foot of the slope.
Prysmian (Ultimate Client : National Grid, South-West Substation Alliance) | Construction
The Swansea North project required the construction and installation of 3 No.132 kV cable circuits and 1 No.
Siemens (Ultimate Client : National Grid) | Construction
A single storey brick extension to an existing 275kV control building within the live HV compound, including all the M&E works.An existing deep drainage run was diverted from under the footprint of the new extension before works on the build could commence.