Latest construction projects from Neary are shown below. Click on a project name for full details, or use the page functions to view any previous projects.
SSE Renewables, Equinor and Eni Plenitude | Construction
Substation civils to facilitate the extension of the 400kV bay for the Dogger Bank Creyke Beck Wind Farm project within the existing National Grid Creyke Beck Substation..
National Grid | Construction
Substation and cable civils to facilitate the installation of HV cables including termination and HV testing between the 400kV National Grid substation and the 132kV UKPN Substation..
National Grid | Construction
Substation and cable civils to facilitate the installation of new XLPE 132kV cables including the removal of existing oil filled 275kV cables along the cable route between the 400kV and the 132kV sections of the Willington National Grid Substation.The contract also included the installation of 11kV ducting including cable installation for the cable diversion for the LVAC site supplies ring main unit within the National Grid substation.
Wind Prospect / Baywa Renawables | Construction
Design and build for the grid connection works for a wind farm with a maximum possible capacity of 20mW located in Northern England, in the East Riding of Yorkshire.Including cable install and wind farm substation build and fit out.
Scottish Power | Construction
A substation extension project carried out for Scottish Power Energy Networks.This project involved a range of site preparation and construction works adjacent to an existing 132kV Substation.
Balfour Beatty | Construction
Works to provide access and enabling for the refurbishment/construction of a high voltage overhead power line at a site near Bristol. Works included top soil stripping, fencing and demarcation gates, construction of approximately 1km of access roads as well as construction of hardstanding, crane pads, and ditch crossings.