Neary Construction Projects


Latest construction projects from Neary are shown below. Click on a project name for full details, or use the page functions to view any previous projects.

Page: 2 of 7
2


Scottish Power | Construction

A new build Substation for Scottish power, this project was delivered successfully by Neary Construction and included construction of around 40 RC foundations for 132/33kV substation equipment, construction of 2 x transformer bunds and around 120 concrete fence foundations and palisade fence erection. Further to this works included drainage works for both clean and oily water, Interceptor installation, troughing, ducting works as well as access and enabling, pathway installation and kerbing works.

Ewehill Substation

Scottish Power | Construction

A large and complex civil engineering project completed for Scottish Power.The project involved the construction of the grid connection cable route and substation build for a 51Mw wind farm around 15km east of Lockerbie.


Glenmont | Construction

Acting as Principal Contractor Neary undertook design, supply and Installation of the grid connection for Todmorden wind farm. Neary undertook every aspect of the works required to construct the contestable grid connection for the 8 turbine wind farm with a capacity of up to 20mW 21MVA to allow for the maximum turbine generation of 2.

Irthlingborough

Siemens | Construction

This contract involved the diversion of numerous 33kV & 11kV cable circuits from within the High Voltage switch yard and the surrounding land into a containerised substation sited on piled stilts. The majority of the cables were installed pre-outage; numerous visits back to site over the last 12 months have seen each cable circuit turned into its final termination position.

Alstom Stafford TX Factory

Alstom | Construction

In order to facilitate the testing of some newly manufactured Quad Boosters the client (Alstom) approached Neary to enquire on a very difficult 132kV cable installation that would be required to deliver test voltages to the new equipment. Having looked at the route it was clear to see why their incumbent suppliers shied away from the proposal.

Staythorpe Heavy Lift Facility

Hyundai Heavy Industries | Construction

This contract necessitated the Project Management of a heavy lift and the subsequent road movement of a 400kV transformer off the River Trent to National Grid Staythorpe substation. The Hyundai transformer had travelled by sea from Korea to Hull where it was then loaded onto an Inland Navigator vessel.

Page: 2 of 7
2