Ewehill Substation


Client | Scottish Power

Division | Construction


A large and complex civil engineering project completed for Scottish Power. The project involved the construction of the grid connection cable route and substation build for a 51Mw wind farm around 15km east of Lockerbie.
This project required the construction of a 132kv – 33Kv Substation for grid connection of the wind farm, situated inside an 80m x 40m substation compound with transformer bases, and internal access roads.
Neary undertook all civil construction works for this project, building all foundations, main transformer bund and plinth, auxiliary transformer bund and plinth , site access roads, drainage, fencing, providing site welfare accommodation, and 24/7 site security for the duration of the build.


Ewehill Substation