Galawhistle Substation


Client | Scottish Power

Division | Construction


A new build Substation for Scottish power, this project was delivered successfully by Neary Construction and included construction of around 40 RC foundations for 132/33kV substation equipment, construction of 2 x transformer bunds and around 120 concrete fence foundations and palisade fence erection.
Further to this works included drainage works for both clean and oily water, Interceptor installation, troughing, ducting works as well as access and enabling, pathway installation and kerbing works.
Works began in Summer 2016 and were completed in September 2016.